Critical Chain Method in Project Management | Buffers & Float

The critical chain method is one of the key tools and techniques for developing a project schedule.

To understand the Critical Chain, we have to look at how a project schedule is developed?

Creating a satisfactory project schedule is often takes lots of iterations.

Read More: The Critical Path Method

Developing a Project Schedule?

We have to go through steps during the development of a schedule like;

  • It is done by evaluating activity sequences, durations, resource needs, and schedule constraints to generate the project schedule model.
  • The schedule model controls the planned start and finish dates for project activities and major milestones based on accuracy. Schedule development can involve extensive review and iterations in time, and resource estimation for the right project schedule model can function as a baseline to track progress.
  • Once we have defined start and end dates, it is recommended to share the detailed information with the project team to avoid conflict in scheduling and resource availability that might also be engaged in some other projects and ensure its validity.

With the passage of time and work progress, the revision and project schedule maintenance process continues and is essential to meet the project completion requirements throughout the project’s duration.

Critical Chain Method

The most vital advantage of this method is that by entering schedule activities, durations, resources, resource reliabilities, and logical relationships into the scheduling tool, it automatically creates the best possible schedule model with planned dates for concluding project activities.

As explained above, the critical chain method (CCM) is one of the schedule method’s key tools. The project team’s help can include buffers in any project schedule path to accommodate any uncertainties and limitations of resources.

It is directly coming from the critical path method technique. It considers the impacts of resource leveling, resource allocation, resource optimization, and activity duration uncertainty or imprecision on the critical path established using the critical path method.

For this, the critical chain method brings the concept of buffers and buffer management. There are three main types of buffers;

Project Buffer

This buffer mainly considers any possible contingencies between the final task and the project finish date. Project delay or early finish will directly impact this buffer. The new finish will result in gains, and any delay will result in a lesser buffer. The project will not be delayed from the original timeline as long as we have sufficient buffer available. It is recommended only to include 50% Approx. of the contingency of task estimate.

Feeding Buffers

These buffers are included in the non-critical chain to avoid any possible delay of the non-critical chain on the critical chain. They are placed between the last task on a non-critical chain and the critical chain.
There is no difference in the calculation of feeding buffer and project buffer. As already explained above, the calculation is dependent on the safety excluded from the tasks on a non-critical chain.

Resource Buffer

Often considered less important than feeding and project buffers, these are kept as a reserve in the critical chain to avoid any delays in the time of need. It can be in the form of human resources or any machine etc.

This technique (CCM) measures the duration of activities without safety margins, logically builds links, and the availability of resources with statistically determined buffers composed of aggregated safety margins of activities at particular points on the project schedule path to bring in the effect of limited resources and project imprecisions.

The resource-oriented critical path is known as the critical chain. The critical chain method technique allows the inclusion of duration buffers, which can be described as non-work schedule activities to manage any unplanned event.

One buffer, including at the very end of the critical chain, shown below in the figure, is known as the project buffer. It safeguards the target finish timeline from slippage along the critical chain.

Additional buffers, known as feeding buffers, as already explained above, are included at every point. A chain of interlinked activities that are not on the critical chain somehow feeds into the critical chain.

Feeding buffers hence safeguard the critical chain from delays along the feeding chains. Every buffer’s size should only consider the imprecision in the timeline for the chain of the interlinked activities before that buffer.

Once we have finalized the buffer schedule activities, the planned activities are scheduled for their latest possible planned start and finish dates. Hence, instead of monitoring the total float of network paths, the critical chain method emphasizes controlling the remaining buffer duration against the remaining duration of chains of activities.

Critical Chain Method

The difference in Float & Buffer

So if you know something about float, you may be inclined towards considering it the same as a buffer. But in fact, they aren’t
Below are a few of the main differences between these two:

  • By definition, a buffer can be described in three different categories: project buffer, feeding buffer, and resource buffer, whereas float is an entirely different thing and can either be total float or free float.
  • By definition, a float is a difference between the length of the critical path and the non-critical path. A float will always have a zero value on the critical path.
  • A buffer is more focused on inaccuracies and takes into account the contingencies. As explained above, the project buffer is usually about 50% of the safety time that has not been considered in the activity estimate duration. It can never have zero value on a critical chain or any other chain.
  • Float is entirely dependent on a critical path, whereas buffer is only relevant in the critical chain.
  • Float is effortless to analyze. It has the same value for all the activities on a non-critical path, any activity can use it partially or fully, and other activities can use the remaining part.
    Similarly, a buffer can also be utilized to accommodate the delay in any other activity. It’s up to the project manager how he/she wants to manage his/her project.

Wrap Up

To summarize the discussion, there is always a chance of a problem occurs in the project execution phase. It’s always recommended to use the Critical chain method during the scheduling phase. It addresses many things that we might not consider if we only focus on critical path methods such as resource availability, budget allocation, etc.

FEATURED POSTS


Download Primavera P6
To download and install Primavera P6 was never that easy as nowadays. By following these steps…

Download Primavera P6

What is PMP?
What does PMP stand for? You are here as you just have heard about PMP, or you know a little already but have some …

What is PMP?

Stakeholder Engagement
A stakeholder is any individual, a group of people or an organization that can affect or be affected positively….

Stakeholer Engagement

Work Breakdown Structure
The heaviest fine is for drifting that is 20,000 for the first time, 40,000 SAR for second and 60,000 SAR for the third violation.

Work Breakdown Structure

Project Management
Project management is how you apply the knowledge, skills, tools, and techniques to get the project management …

Project Management

Gantt Chart
A Gantt chart is also known as bar chart represents a project plan by making each task into a bar and …

Gantt Chart

Planning Engineer
Planning Engineer is considered the right-hand of a Project Manager as he floats the information about project…

Planning Engineer

Team Development
Dr. Bruce W. Tuckman, a psychologist, published a theory in 1965 called ‘Tuckman’s Stages of Group Development’.

Team Development


1 thought on “Critical Chain Method in Project Management | Buffers & Float”

  1. When you say 50%, how would you consider odd numbers? Let’s say duration of project is 15 weeks. What would the project buffer be, 7 or 8? I guess I’m trying to figure out how to show it on my excel.

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top